So you've made the decision. You're building a pool. Congratulations — now comes the part where the excitement meets reality, and reality involves permits, mud, and a whole lot of waiting for things you didn't know you had to wait for.

The good news is that Richmond-area homeowners who go in with a clear picture of the construction timeline tend to have a much smoother experience. When you know what's coming, you can plan around it, make decisions on time, and avoid the delays that happen when homeowners are caught off guard at critical moments. Here's what the journey actually looks like, month by month.

Before Anything Else: The Design and Planning Phase (Weeks 1–4)

Most Richmond pool projects begin with a design consultation, and this phase deserves more time than many homeowners give it. Your builder will assess the yard, discuss your vision, and start translating ideas into a workable design. This is when you'll make foundational decisions about shape, depth, water features, decking material, and equipment.

Don't rush this step. Changes made on paper cost nothing. Changes made after excavation cost a lot.

Once the design is finalized, your builder will prepare the drawings and specifications needed for the permit application. In Chesterfield, Henrico, and the City of Richmond, permit processing times vary — typically running anywhere from two to six weeks depending on the jurisdiction and time of year. Spring is the busiest permit season, so homeowners who begin the process in late winter often get faster turnaround.

Key decisions to lock in before permits are submitted:

Month Two: Permits Clear and the Excavation Begins

Once permits are approved, things move fast — and get loud. Excavation is the most dramatic single day of the entire project. A crew arrives with heavy equipment, and within hours your backyard looks like a construction site, because it is one.

In Richmond, excavators deal with a mix of clay-heavy soil and occasional rock, both of which can affect the timeline. Clay soil expands when wet, which is why your builder pays close attention to weather forecasts during this phase. Significant rain right after excavation can complicate the next steps, so expect your builder to move quickly from dig to steel installation.

After excavation, the steel reinforcement framework — the rebar skeleton of your pool — goes in. This is when the shape of your pool becomes real and three-dimensional for the first time. Many homeowners visit the site during this phase just to see it taking form.

Month Two to Three: Gunite or Shotcrete Application

For most inground pools in the Richmond area, the shell is formed using gunite or shotcrete — a pneumatically applied concrete mixture that's sprayed over the steel framework. This is a skilled process, and the quality of application matters enormously for the long-term integrity of your pool.

After the shell is applied, it enters a curing period that typically lasts seven to ten days. During this time, the concrete needs to stay moist, and your builder's crew will wet it down regularly. This isn't a step to skip or shorten — proper curing is what gives the shell its strength.

Richmond's weather plays a role here. Extreme heat in July and August can accelerate drying too quickly if the shell isn't properly managed, while temperatures below freezing can halt the curing process entirely. Experienced local builders schedule this phase carefully and keep an eye on the forecast.

Month Three: Plumbing, Electrical, and Equipment Installation

With the shell cured, the focus shifts to the systems that make the pool function. Plumbing lines for circulation, returns, drains, and any water features are installed and pressure-tested. Electrical work follows, covering lighting, the pump, any automation systems, and the equipment pad.

This phase is where having licensed, experienced subcontractors matters most. Virginia requires licensed electrical contractors for pool wiring, and any shortcuts here create serious safety risks. Ask your builder who handles the electrical work and confirm their credentials.

Equipment is also set and connected during this phase — your pump, filter, heater (if included), and any smart-home automation controls. This is a good time to ask your builder for a walkthrough of how everything operates so you're not learning it all at once on opening day.

Month Three to Four: Tile, Coping, and Decking

Now the pool starts looking like something you'd actually want to swim in. Tile is applied at the waterline, coping stones are set around the perimeter, and decking work begins. These are among the most visually significant choices you made back in the design phase, and seeing them installed is usually a highlight for homeowners.

Decking can take one to three weeks depending on the material and square footage. Concrete decking, stamped concrete, pavers, and natural stone all have different installation timelines. Weather matters here too — freshly poured concrete decking needs protection from rain for the first 24 to 48 hours.

Month Four to Five: Interior Finish and the Water Fill

The interior plaster or finish surface is one of the last major construction steps. Whether you've chosen traditional white plaster, a quartz aggregate blend, or a pebble finish, this application transforms the shell into a finished pool.

After the finish is applied, water filling begins almost immediately — within hours — to prevent the plaster from drying unevenly. Filling a typical residential pool takes 12 to 24 hours depending on pool size and water pressure.

The startup process that follows is chemistry-intensive. Your builder's team will balance the water carefully during the first two weeks, and you'll have some restrictions on swimming while the finish cures properly. Follow these instructions. The startup period directly affects how your finish looks and performs for years to come.

Month Five and Beyond: Final Inspections and the First Swim

Before you can legally use the pool, final inspections must be completed and approved. Inspectors will verify fencing, electrical work, and overall compliance with local code. This step is non-negotiable, and reputable builders build it into the schedule from the start.

Once inspections are cleared and startup chemistry is complete, the pool is yours.

From initial consultation to that first cannonball, most Richmond pool projects run five to seven months when the process flows smoothly. Spring starts often lead to summer finishes. Fall starts can push completion into the following spring, particularly if cold weather interrupts curing or plaster application.

The homeowners who enjoy the process most are the ones who stay engaged, make decisions promptly, and trust a builder who communicates clearly every step of the way. Find that builder, and the wait is absolutely worth it.

All Articles

Related Articles

What's Hot in Richmond Pools Right Now: 5 Design Trends Worth Talking About in 2024

What's Hot in Richmond Pools Right Now: 5 Design Trends Worth Talking About in 2024

Bargain Pool Builders: Why the Lowest Bid Could Leave Richmond Homeowners Underwater

Why Going It Alone on Pool Installation Could Cost Richmond Homeowners a Fortune

Why Going It Alone on Pool Installation Could Cost Richmond Homeowners a Fortune